The contractor has completed the concrete curb & gutter installation on the project area and has begun concrete pavement installation. Access to the Courthouse Square will be extremely limited during concrete pavement installation.

Access to the Courthouse building will only be available via the east roadway entering the Courthouse Square for both pedestrian and vehicle traffic. Please use caution when navigating the Courthouse Square construction zone as a large volume of concrete trucks and construction equipment will be on site.

Please contact the following people with further questions:

Will Hermanson – Construction Manager, Schmidt Construction, Inc.: 507-616-6536
Jim Doering – Public Works Project Coordinator, City of Redwood Falls: 507-430-5904
Joe Smith, E.I.T. – Resident Project Representative, Bolton & Menk, Inc.: 507-676-3751