Courthouse Square Update – 9.13.19

The contractor has installed the gravel base from the north entrance to the Courthouse Square through the west entrance to the Courthouse Square.

Construction progress has been limited this week due to the rainfall events. The contractor is working on the watermain on the east side of the Courthouse Square and is proposing to complete the connection to the Courthouse water service on Saturday 9/14/19.

Beginning Monday 9/16/19 the east roadway entering the Courthouse Square will be closed. Vehicle access will be provided from the north and west roadways entering the Courthouse Square. Construction will encroach on the main east entrance to the Courthouse; however, pedestrian traffic will continue to be maintained.

Please contact the following people with further questions:

Will Hermanson – Construction Manager, Schmidt Construction, Inc.: 507-616-6536
Jim Doering – Public Works Project Coordinator, City of Redwood Falls: 507-430-5904
Joe Smith, E.I.T. – Resident Project Representative, Bolton & Menk, Inc.: 507-676-3751