Lake Redwood Reclamation Project Update

The first step is underway, to construct the Confined Disposal Facility (CDF) which will hold and dewater the dredged material over time.

Crews from Mathiowetz Construction worked on the placement of storm sewer piping on the east and west side of the project area to intercept and relocate existing drainage lines around the project site.  Crews continue topsoil stripping for placement of the berm that will confine and dewater dredge spoils from Lake Redwood.  Berm construction has begun in areas where it is not in conflict with other phases of the project.

Weather permitting the project is intended to be substantially complete this year. Stay tuned for further drone footage as the project progresses.